Match the following terms with the items below:
-Static budget
A) Difference between the actual amount and the flexible budget amount
B) A budget that specifies costs for a range of activity
C) A budget for a particular level of activity
D) A report that compares actual with planned costs
E) Actual variable overhead − (SVOR × Actual hours)