Serenity Equestrian Corporation produces high-quality leather saddles. The company has a standard cost system and has set the following standards for materials and labour:
During the year, Serenity Equestrian Corporation produced 150 saddles. Actual leather purchased was 3,100 strips at $12 per strip. There were no beginning or ending inventories of leather. Actual direct labour was 2,500 hours at $16 per hour.
-Refer to the Figure.What are the labour rate variance and the labour efficiency variance,respectively?
A) $2,250 U and $4,000 U
B) $2,250 F and $4,000 F
C) $2,500 U and $3,750 U
D) $2,500 F and $3,750 F
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Match each of the following terms with
Q38: Match each of the following calculations with
Q53: Bear Company uses a standard costing
Q55: Bi-land Company's standard cost is $150,000.
Q57: Aqua Company produces aquariums. During the
Q60: The Fantastic Tool Company (Mexico Division) produced
Q61: Meow Meow manufactures gourmet cat food.During
Q62: If the target cost is less than
Q128: Which formula is used to calculate the
Q201: Matching<br>Match each item with the correct statement