Multiple Choice
Allan Company manufactures overalls. During the year, it manufactured 125,000 overalls, using 2.9 hours of direct labour at a rate of $6.25 per hour. The materials and labour standards for manufacturing the overalls are as follows:
Allan required 600,000 m at $1.95 per metre to make the 125,000 overalls.
-Refer to the Figure.What is Allan's materials usage variance?
A) $48,750 U
B) $48,750 F
C) $50,000 U
D) $50,000 F
Correct Answer:

Verified
Correct Answer:
Verified
Q112: During March, a small roofing company purchased
Q114: How do standard cost systems enhance operational
Q115: Green Lawn Corporation wants to produce
Q116: During March,Raining Unlimited produced 5,500 umbrellas from
Q118: During the month of December, Cakers Express
Q119: Meeds Company uses the following rule to
Q120: AirSoar Company produces model airplanes. During August,
Q121: High Fly Company manufactures model airplanes.
Q122: Match each of the following calculations with
Q131: Ideal standards demand maximum efficiency and can