Allan Company manufactures overalls. During the year, it manufactured 125,000 overalls, using 2.9 hours of direct labour at a rate of $6.25 per hour. The materials and labour standards for manufacturing the overalls are as follows:
Allan required 600,000 m at $1.95 per metre to make the 125,000 overalls.
-Refer to the Figure.What is the entry to close the variances of labour and materials?
A) Materials Price Variance 30,000Materials Usage Variance 50,000Labour Efficiency Variance 75,000Cost of Goods Sold 155,000Cost of Goods Sold 90,625Labour Rate Variance 90,625
B) Materials Price Variance 31,250Materials Usage Variance 48,750Labour Efficiency Variance 78,125Cost of Goods Sold 158,125Cost of Goods Sold 93,750Labour Rate Variance 93,750
C) Cost of Goods Sold 155,000Materials Price Variance 30,000Materials Usage Variance 50,000Labour Efficiency Variance 75,000Labour Rate Variance 90,625Cost of Goods Sold 90,625
D) Cost of Goods Sold 158,125Materials Price Variance 31,250Materials Usage Variance 48,750Labour Efficiency Variance 78,125Labour Rate Variance 93,750Cost of Goods Sold 93,750
Correct Answer:

Verified
Correct Answer:
Verified
Q17: Match each of the following terms with
Q67: Action Company's standard cost is $600,000.The
Q68: Overland Company is considering manufacturing a
Q69: Aqua Company produces aquariums. During the
Q70: What are price standards based on?<br>A)the amount
Q72: Min Company has developed the following
Q73: Which formula is used to compute the
Q74: Which of the following statements is characteristic
Q76: Assume that SQ = Standard Quantity,SP =
Q89: Kaizen costing provides fixed standards which reflect