Multiple Choice
Termination by addition occurs when:
A) Scope creep adds too many activities to the project that prevent it from being completed on time or within budget.
B) The project is so successful that it becomes institutionalized.
C) A new project is added to the organization and it commands all of the resources for the original project.
D) New members join the project team once the project has begun and their skills are insufficient to successfully complete the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q53: The primary goal in requiring a project
Q54: Lessons-learned analysis is BEST described as:<br>A)A bookkeeping
Q55: A project that is terminated by extinction
Q56: The final project report should answer questions
Q57: What is the difference between natural termination
Q59: In the United States,a Private Finance Initiative
Q60: What are three different ways that a
Q61: Loss of team identity is:<br>A)An emotional staff
Q62: What can a project organization do to
Q63: The difference between a manager with ten