An ex-gratia claim made when a project is closed down is made when:


A) There is no contractual basis for a claim.
B) The project company fails to perform to the terms of the contract.
C) The client company fails to perform to the terms of the contract.
D) A third party causes either the client or project company to fail to perform to the terms of the contract.