Multiple Choice
A hospital decided to streamline its surgical suite operation. The nurses in charge studied the amount of time patients actually spent in various activities. They found that, on average, a patient scheduled for an operation spent about 2 hours waiting and 2.5 hours moving from the lab to the X-ray to the operating room. The average operation takes 90 minutes. What is the MCE?
A) 25.0%
B) 33.3%
C) 66.7%
D) 75.0%
Correct Answer:

Verified
Correct Answer:
Verified