Allan Company manufactures overalls. During the year, it manufactured 125,000 overalls, using 2.9 hours of direct labour per unit at a rate of $6.25 per hour. The materials and labour standards for manufacturing the overalls are as follows:
The company required 600,000 m at $1.95 per metre to make the 125,000 overalls.There were no beginning or ending inventories.
-Refer to Allan Company. What is the entry to record the purchase of materials?
A) Materials 1,170,000
Materials Price Variance 30,000
Accounts Payable 1,200,000
B) Materials 1,200,000
Materials Price Variance 30,000
Accounts Payable 1,170,000
C) Materials 1,218,750
Materials Price Variance 31,250
Accounts Payable 1,250,000
D) Materials 1,250,000
Materials Price Variance 31,250
Accounts Payable 1,218,750
Correct Answer:

Verified
Correct Answer:
Verified
Q15: The materials price variance is computed using
Q128: Which formula is used to calculate the
Q129: Match each of the following calculations with
Q130: Bi-land Company<br>Bi-land Company's standard cost is
Q131: Ideal standards demand maximum efficiency and can
Q132: Allan Company<br>Allan Company manufactures overalls. During
Q134: The standard quantity of materials allowed can
Q135: What is NOT characteristic of control limits?<br>A)
Q136: How are costs assigned in a standard
Q138: Refer to RJB Builders. What was the