Multiple Choice
Scoresby Co.uses 6 machine hours and 2 direct labor hours to produce Product X.It uses 8 machine hours and 16 direct labor hours to produce Product Y.Scoresby's Assembly and Finishing departments have factory overhead rates of $240 per machine hour and $160 per direct labor hour,respectively.How much overhead cost will be charged to the two products?
A) Product X = $3,200; Product Y = $9,600
B) Product X = $800; Product Y = $800
C) Product X = $1,760; Product Y = $4,480
D) Product X = $1,440; Product Y = $2,560
Correct Answer:

Verified
Correct Answer:
Verified
Q52: Pinacle Corp.budgeted $700,000 of overhead cost for
Q53: Estimated activity-base usage quantities are the total
Q54: The Sawtooth Leather Company manufactures leather handbags
Q55: Everest Co.uses a plantwide factory overhead rate
Q58: Determine the overhead from both production departments
Q59: Calculate the cost of services for a
Q60: Using the single plantwide factory overhead rate
Q61: Use of a plantwide factory overhead rate
Q76: Activity-based costing can be used to allocate
Q77: Multiple production department factory overhead rates are