Solved

Use the Information Below to Answer the Following Question(s) \quad

Question 166

Multiple Choice

Use the information below to answer the following question(s) .
Sierra Ceramics makes custom ceramic tiles. During March, the company started and finished Job #231. Job #231 consists of 2,000 tiles; each tile sells for $12.00. The company's records show the following direct materials were requisitioned for Job #231.
Basic terra cotta tiles: \quad 2,000 units at $2.00 per unit
Specialty paint: \quad \quad \quad 5 quarts at $4.00 per quart
High gloss glaze: \quad \quad 3 quarts at $10.00 per quart

Labour time records show the following employees worked on Job #231:
Emily Jergens: \quad \quad \quad 20 hours at $22 per hour
Dan Evrard: \quad \quad \quad \quad 12 hours at $15 per hour

Sierra Ceramics allocates manufacturing overhead at a rate of $25 per direct labour hour.
-At Sierra Ceramics what is the total amount of direct materials, direct labour, and manufacturing overhead that should be shown on Job #231's job cost record?


A) $5,470
B) $4,670
C) $800
D) $24,000

Correct Answer: