Multiple Choice
Use the information below to answer the following question(s) .
The following account balances at the beginning of January were selected from the general ledger of Sailor Manufacturing Company:
Work in process inventory $0
Raw materials inventory $26,000
Finished goods inventory $46,000
Additional data:
1) Actual manufacturing overhead for January amounted to $62,000.
2) Total direct labour cost for January was $57,000.
3) The predetermined manufacturing overhead rate is based on direct labour cost. The budget for the year called for $300,000 of direct labour cost and $360,000 of manufacturing overhead costs.
4) The only job unfinished on January 31 was Job No. 1002, for which total direct labour charges were $6,300 (800 direct labour hours) and total direct material charges were $12,000.
5) Cost of direct materials placed in production during January totaled $101,000.
6) January 31 balance in raw materials inventory was $32,000.
7) Finished goods inventory balance on January 31 was $34,500.
-What is the cost of goods manufactured for January at Sailor Manufacturing Company?
A) $200,540
B) $179,640
C) $226,400
D) $205,500
Correct Answer:

Verified
Correct Answer:
Verified
Q134: The predetermined manufacturing overhead rate is calculated
Q287: Dryson Company uses a job costing system.
Q288: Use the information below to answer the
Q289: Wesley Corporation charged Job 110 with $12,000
Q290: Assigning direct costs to a cost object
Q291: Manufacturing overhead would include<br>A) indirect labour costs
Q293: Custom Cedar Products (CCP) manufactures a line
Q295: Use the information below to answer the
Q296: Use the information below to answer the
Q297: Assigning manufacturing overhead costs and other indirect