Multiple Choice
The estimated overhead for the cost pool,machine set-ups,is $180 000.The machines in the pool produce three products: X (300 set-ups) ; Y (200 set-ups) and Z (500 set-ups) .The amount of machine set-up costs that should be allocated to product Y is:
A) $36 000
B) $90 000
C) $54 000
D) $180 000
Correct Answer:

Verified
Correct Answer:
Verified