Multiple Choice
Fact Pattern 18-B1 (Questions B9-B10 apply)
Moses sells an apartment building to Noelle with a promise to install a new heating and air conditioning system before September 1.The following February 1,Moses sends Ollie,an HVAC technician,to begin the installation.Noelle orders Ollie to leave and refuses to make further payments to Moses,who files a suit against Noelle.
-Refer to Fact Pattern 18-B1.Noelle's refusal to make further payments is most likely
A) a material breach.
B) complete performance.
C) excused by Moses's failure to timely install the ventilation system.
D) substantial,but not complete,performance.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: A contractual obligation may not be discharged
Q16: The law allows an innocent party to
Q18: OnTrack Rehabilitation Center signs an agreement with
Q21: A party who in good faith performs
Q22: In most contracts,promises of performance are not
Q24: Fact Pattern 18-B2 (Questions B11-B12 apply)<br>Business Computer
Q25: A contract will be discharged if supervening
Q30: Even-Bilt Construction contracts to build a warehouse
Q37: Adrian operates a recycled metals business and
Q52: When an anticipatory repudiation occurs, it is