Multiple Choice
Porches & Verandas, Inc., agrees to build a screen porch for Quinn, but fails to complete the job. Quinn hires Ramadas, Inc., to finish the project. Quinn may recover from Porches & Verandas
A) the contract price less costs of materials and labor.
B) the contract price.
C) the costs needed to complete construction.
D) profits plus the costs incurred up to the time of the breach.
Correct Answer:

Verified
Correct Answer:
Verified