In Your First Job You Must Set Up an Assembly

Question 12

Essay

In your first job you must set up an assembly line to assemble a computer mouse. The precedence diagram below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast output rate) is 60 units per shift. In your first job you must set up an assembly line to assemble a computer mouse. The precedence diagram below is defined with task times in parentheses and stated in minutes. There are 480 minutes of assembly time per shift and there is one shift. The forecast output rate) is 60 units per shift.    a. Compute the cycle time per unit in minutes. b. Compute the minimum number of workstations required. c. Use the longest-task-time heuristic to balance the assembly line. d. Compute the efficiency of your assembly line.
a. Compute the cycle time per unit in minutes.
b. Compute the minimum number of workstations required.
c. Use the longest-task-time heuristic to balance the assembly line.
d. Compute the efficiency of your assembly line.

Correct Answer:

verifed

Verified

a. Cycle time = 480/60 = 8 minutes per u...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions