Solved

Using the Data Below, Find the EOQ, the Total Annual

Question 22

Essay

Using the data below, find the EOQ, the total annual cost associated with the economic order quantity, and the reorder point.
 Annual Demand:  8,000 units  Weeks Operating: 52/ year  Ordering Cost: $35/ arder  Holding Cost: $4/ unityear  Lead-Time: 3 weeks \begin{array} { l l } \text { Annual Demand: } & \text { 8,000 units } \\\text { Weeks Operating: } & 52 / \text { year } \\\text { Ordering Cost: } & \$ 35 / \text { arder } \\\text { Holding Cost: } & \$ 4 / \text { unityear } \\\text { Lead-Time: } & 3 \text { weeks }\end{array}

Correct Answer:

verifed

Verified

blured image
Q* = Sq. root of (2 x 8000 x 35/4) = 3...