Solved

Using the Data Below, Find the EOQ, the Total Annual

Question 70

Essay

Using the data below, find the EOQ, the total annual cost associated with the economic order quantity, and the reorder point.
 Annul Demand: 15,000 units  Weeks Operating: 52 weekslyear  Ordering Costs: $60/0rder Holding Costs: $7/h wetyear  Lead-Time: 5 weeks \begin{array} { l l } \text { Annul Demand: } & 15,000 \text { units } \\\text { Weeks Operating: } & 52 \text { weekslyear } \\\text { Ordering Costs: } & \$ 60 / 0 r d e r \\\text { Holding Costs: } & \$ 7 / h \text { wetyear } \\\text { Lead-Time: } & 5 \text { weeks }\end{array}

Correct Answer:

verifed

Verified

blured image
Q* = Sq. root of (2 x 15000 x 60/7) = ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge