Multiple Choice
The Shortest Processing Time (SPT) rule
A) Ensures that due dates are met
B) Maximizes average flow-time
C) Minimizes resource utilization
D) Minimizes work in process inventory
Correct Answer:

Verified
Correct Answer:
Verified