Multiple Choice
ABC Manufacturing uses a Kanban system for a component.The daily demand is 800 units.Each container has a combined waiting and processing time of 0.34 days.If the container size is 50 and efficiency (safety) factor is 9 percent, how many Kanban card sets should be authorized (round up) ?
A) 5 sets
B) 6 sets
C) 7 sets
D) 8 sets
Correct Answer:

Verified
Correct Answer:
Verified