Essay
A manufacturing company is planning to use PERT to setup a project for a new production line. For this project, they have established the following activities, precedence relationships, and time estimates in days:
a. What is the expected duration for activity b?
b. What is the variance of activity d?
c. How many paths are there in the network?
d. What is the earliest finish EF) time for activity e?
e. What is the slack in days for activity c
f. What is the critical path
g. What is the duration of the critical path in days
h. What is the standard deviation of the critical path
i. What is the probability of completing the project within 50 days?
Correct Answer:

Verified
a. te = to + 4tView Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q3: Which step in the project management process
Q7: The following network shows all the
Q22: Explain the role of the project managers
Q30: Activity times must be estimated from historical
Q41: Which of the following is least related
Q43: A type of organization that can result
Q43: All activities on the critical path have
Q55: In which stage in the project life
Q69: Strong leadership is an impediment to project
Q85: A slack of 2 means the project