Multiple Choice
The aggregate plan helps manufacturing with all of the following except:
A) whom to employ
B) how much work to subcontract
C) how much inventory can be held
D) when to add/subtract employees
E) when to use overtime
Correct Answer:

Verified
Correct Answer:
Verified