Given the Following Calculate (A)cost Using a Level Production Plan,(b)cost

Question 57

Multiple Choice

Given the following calculate (a) cost using a level production plan,(b) cost using a chase aggregate plan,and identify the lowest cost option.In the level production plan backorders are allowed but for each unfilled order it costs the company $10/unit.The employees work an 8 hour day and overtime is not allowed
Given the following calculate (a) cost using a level production plan,(b) cost using a chase aggregate plan,and identify the lowest cost option.In the level production plan backorders are allowed but for each unfilled order it costs the company $10/unit.The employees work an 8 hour day and overtime is not allowed     A) A=5834,B = 5472,C = level B) A=5472,B = 5834,C = level C) A=5834,B = 5472,C = chase D) A=5472,B = 5834,C = chase E) A =5834,B = 5472,C = either


A) A=5834,B = 5472,C = level
B) A=5472,B = 5834,C = level
C) A=5834,B = 5472,C = chase
D) A=5472,B = 5834,C = chase
E) A =5834,B = 5472,C = either

Correct Answer: