Multiple Choice
Calculate the total cost to meet the demand using a chase production plan with overtime. Once overtime is approved the workers are on the job 12 hours each day for the full period.
A) $72,960
B) $73,460
C) $73,660
D) $76,800
E) $77,175
Correct Answer:

Verified
Correct Answer:
Verified