Multiple Choice
Budgeted variable overhead for the year is $150,000.Expected activity is 30,000 standard direct labor hours.The actual hours worked were 15,000 and the standard hours allowed for actual production were 18,000.The variable overhead efficiency variance is:
A) $14,600 F.
B) $18,000 F.
C) $30,000 F.
D) $15,000 F.
E) None of these
Correct Answer:

Verified
Correct Answer:
Verified
Q30: All of the following are true except<br>A)
Q31: The _ is the difference between the
Q32: The two variances for fixed overhead are<br>A)
Q33: The _ can be used to compute
Q34: During June, Cisco Company produced 12,000 chainsaw
Q36: Match the variance with its correct calculation.<br>-Actual
Q37: James Company manufactures t-shirts.During the year, it
Q38: The sum of the price and usage
Q39: Which of the following is true regarding
Q40: Which of the following formulas is used