Which Two of the Following Methods of Project Analysis Are

Question 73

Multiple Choice

Which two of the following methods of project analysis are most biased towards short-term projects?
I.Internal rate of return
II.Accounting rate of return
III.Payback
IV.Discounted payback


A) I and II only
B) III and IV only
C) II and III only
D) I and IV only
E) II and IV only