Multiple Choice
A project has an initial cash inflow of $95,500 and cash flows of -$48,700 in Year 1 and -$57,200 in Year 2.The discount rate is 9 percent.Should this project be accepted or rejected based on IRR? Why?
A) Accepted: because the IRR of 6.98 percent is less than the discount rate
B) Accepted: because the IRR of 8.21 percent is less than the discount rate
C) Accepted: because the IRR of 8.78 percent is less than the discount rate
D) Rejected: because the IRR of 8.21 percent is less than the discount rate
E) Rejected: because the IRR of 6.98 percent is less than the discount rate
Correct Answer:

Verified
Correct Answer:
Verified
Q26: A project produces annual net income of
Q27: Nadine always makes the final accept/reject decision
Q28: The present value of an investment's future
Q29: A project has a net present value
Q30: The modified internal rate of return is
Q32: What are the limitations of the IRR
Q33: Miller's is considering a 2-year expansion project
Q34: A project costs $22,900 to initiate.It is
Q35: What is the key reason why a
Q349: Which one of the following statements is