Multiple Choice
Precise Machinery is analyzing a proposed project.The company expects to sell 2,100 units,give or take 5 percent.The expected variable cost per unit is $260 and the expected fixed costs are $589,000.Cost estimates are considered accurate within a plus or minus 4 percent range.The depreciation expense is $129,000.The sales price is estimated at $775 per unit,give or take 2 percent.The tax rate is 34 percent.The company is conducting a sensitivity analysis with fixed costs of $590,000.What is the OCF given this analysis?
A) $337,975
B) $285,350
C) $368,250
D) $374,874
E) $414,350
Correct Answer:

Verified
Correct Answer:
Verified
Q63: Which one of the following statements concerning
Q64: A proposed project has fixed costs of
Q65: Precise Machinery is analyzing a proposed project.The
Q66: The accounting break-even production quantity for a
Q67: Precise Machinery is analyzing a proposed project.The
Q69: Mr.Bear,your boss,will only agree to accept a
Q70: A proposed project has fixed costs of
Q71: An analysis which combines scenario analysis with
Q72: You are the manager of a project
Q73: Forecasting risk emphasizes the point that the