Precise Machinery Is Analyzing a Proposed Project

Question 68

Multiple Choice

Precise Machinery is analyzing a proposed project.The company expects to sell 2,100 units,give or take 5 percent.The expected variable cost per unit is $260 and the expected fixed costs are $589,000.Cost estimates are considered accurate within a plus or minus 4 percent range.The depreciation expense is $129,000.The sales price is estimated at $775 per unit,give or take 2 percent.The tax rate is 34 percent.The company is conducting a sensitivity analysis with fixed costs of $590,000.What is the OCF given this analysis?


A) $337,975
B) $285,350
C) $368,250
D) $374,874
E) $414,350

Correct Answer: