Multiple Choice
Your company is reviewing a project with estimated labor costs of $21.20 per unit,estimated raw material costs of $37.18 a unit,and estimated fixed costs of $20,000 a month.Sales are projected at 42,000 units over the one-year life of the project.All estimates are accurate within a range of plus or minus 4 percent.What are the total variable costs for the worst-case scenario?
A) $890,400
B) $1,561,560
C) $2,448,037
D) $2,451,960
E) $2,691,960
Correct Answer: