Question 37

Multiple Choice

Which of the following is the correct mathematical expression to calculate the fixed overhead production-volume variance?


A) static-budget amount - flexible-budget amount
B) flexible-budget amount - actual costs incurred
C) actual costs incurred - fixed overhead allocated for actual output
D) budgeted fixed overhead - fixed overhead allocated for actual output

Correct Answer: