Multiple Choice
Ventaz Corp manufactures small windows for back yard sheds. Historically, its demand has ranged from 30 to 50 windows per day with an average of 41. Alex is one of the production workers and he works eight hours a day, five days a week. Each order is one window and each window takes 10 minutes.
What is the cycle time for an order?
A) 10 minutes per window
B) 100.00 minutes per window
C) 39.29 minutes per window
D) 500.00 minutes per window
Correct Answer:

Verified
Correct Answer:
Verified