The tool crib at a large manufacturing company is responsible for providing tools to the factory workers on demand. The tool crib has a variable demand. Historically, its demand has ranged from 340 to 600 small tools per day with an average of 470. Diane, the tool crib attendant, works eight hours a day, five days a week. Each order is for one small tool and each small tool takes Diane 1 minute to retrieve from the bins.
What is the cycle time for an order? (Round the final answer to the first decimal place.)


A) 1.0 minutes per tool
B) 22.5 minutes per tool
C) 23.5 minutes per tool
D) 24.5 minutes per tool