Assembly Department of Zahra Technologies Had 200 Units as Work

Question 104

Multiple Choice

Assembly department of Zahra Technologies had 200 units as work in process at the beginning of the month. These units were 45% complete. It has 300 units which are 35% complete at the end of the month. During the month, it completed and transferred 500 units. Direct materials are added at the beginning of production. Conversion costs are allocated evenly throughout production. Zahra uses weighted-average process-costing method. Calculate the total equivalent units in ending inventory for assignment of conversion costs?


A) 200 units
B) 105 units
C) 195 units
D) 300 units