Multiple Choice
Which of the following is an objective of value engineering?
A) to reduce cost by eliminating all value-added activities
B) to streamline and add non-value added activities
C) to reduce the total cost of the product
D) to understand competitors' product design
Correct Answer:

Verified
Correct Answer:
Verified