In Activity-Based Costing, the First Step in Assigning Costs Is

Question 41

Multiple Choice

In activity-based costing, the first step in assigning costs is to


A) analyze all nonvalue-adding activities to determine if they are necessary support areas.
B) accumulate costs for each activity.
C) identify and classify each activity.
D) separate nonvalue-adding activities from value-adding activities.

Correct Answer: