Lopar Company Uses a Predetermined Overhead Rate Based on Direct

Question 89

Multiple Choice

Lopar Company uses a predetermined overhead rate based on direct labor dollars. Lopar Company estimated that its 2010 overhead would total $938,000 and that 2010 direct labor costs would be $670,000. During 2010, actual overhead costs were $960,000, and actual direct labor costs were $700,000. By how much was Lopar's overhead over- or underapplied?


A) $20,000 overapplied
B) $20,000 underapplied
C) $18,000 overapplied
D) $10,000 underapplied