Multiple Choice
On 1 January 2015,Romulus Ltd signed a contract worth $21 000 000 to construct a light rail from A to B.The light rail was to be built over three years,with progress payments of $7 000 000 to be made at the end of each year.Estimated costs were $15 000 000 and the following costs incurred and paid by Romulus Ltd were in accordance with estimates and represented the percentage completed in each year: The project was completed in December 2017.
-Using the percentage of completion method,what profit would Romulus Ltd report in 2015?
A) $800 000
B) $2 000 000
C) $3 200 000
D) $1 300 000
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Multi-Storey Builders Ltd had a large three-year
Q3: Highrise Constructions Ltd had a large three-year
Q4: Revenue from a credit sale should not
Q5: The profit for a particular project of
Q6: The percentage of completion profit for a
Q7: Leslie Ltd has found an error in
Q8: Revenue should be recognised when: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6113/.jpg"
Q9: Toy Company manufactures toy koalas.Transactions for the
Q10: Junction Company had the following transactions,among others,during
Q11: Leslie Ltd has found an error in