Multiple Choice
Figure 4-20 Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications) . Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs have been assigned to each activity using direct tracing and resource drivers: Owens produces two models: Model X and Model Y. The following table shows how the two products consume activity.
Refer to Figure 4-20. First, determine the overhead costs assigned to model D using the two most expensive activities for cost pools. The costs of the two relatively inexpensive activities are allocated to the two most expensive activities in proportion to their costs. (Round to two decimal places.) What is the error in the overhead cost assigned to model D using ABC (4 driver model) as the benchmark?
A) $180,030
B) $240,700
C) $313,330
D) $626,650
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Figure 4-8 Tandem Company manufactures two products
Q5: The following information pertains to Whitestone Industries
Q6: Figure 4-6 The Fast & Furious Company
Q7: Figure 4-11 Longview Manufacturing Company manufactures two
Q10: Figure 4-1 The Foremost Company predicted factory
Q11: The following information is provided by the
Q36: The justification for not using a departmental
Q154: An activity-based costing system traces costs to
Q169: A possible solution to overcome distortions caused
Q171: If activity-based costing is used, modifications made