Figure 4-20 Quasi-Tech Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications) . Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. Costs have been assigned to each activity using direct tracing and resource drivers: Owens produces two models: Model X and Model Y. The following table shows how the two products consume activity.
Refer to Figure 4-20. What are the global consumption ratios of Model C and D respectively? (round to two decimal places)
A) 0.20; 0.80
B) 0.42; 0.58
C) 0.56; 0.44
D) 0.84; 0.16
Correct Answer:

Verified
Correct Answer:
Verified
Q10: The nonfinancial and financial data that describe
Q42: Using the before-the-fact simplification method TDABC eliminates
Q51: All of the following are unit-based activity
Q53: A predetermined overhead rate is calculated using
Q59: A costing system that uses actual costs
Q104: Figure 4-12 The Gardenview Corporation has identified
Q107: The Roanoke plant of the Virginia Company
Q112: Figure 4-13 The Molotov plant of Kaboom
Q114: Figure 4-6 The Fast & Furious Company
Q168: All of the following are non-unit-based activity