Multiple Choice
Figure 3-8 The following computer printout estimated overhead costs using multiple regression: During the year the company used 1,000 setup hours and 500 parts.
Refer to Figure 3-8. What is the predicted overhead cost?
A) $2,500
B) $75,000
C) $76,000
D) none of these