Multiple Choice
The Kanban system is used to
A) ensure parts or materials are available when needed.
B) signal when preventive maintenance is needed.
C) signal when a defective unit has been produced.
D) ensure idle time of workers is not wasted.
Correct Answer:

Verified
Correct Answer:
Verified
Q17: JIT avoids shutdowns due to materials shortages
Q91: Labour and overhead incurred for rework of
Q92: In the zero-defects view of quality,<br>A)control costs
Q93: At the beginning of the year,
Q94: A withdrawal Kanban specifies<br>A)how much should be
Q95: Which of the following stages comes first?<br>A)Introduction<br>B)Growth<br>C)Development<br>D)Decline
Q96: The just-in-time (JIT) approach to inventory management<br>A)allows
Q98: Clark, SA., sells one of its
Q99: Which of the following is an example
Q101: _ are the costs of activities performed