Knoxville Manufacturing Company produces X and Y with contribution margins per unit of $10 and $90, respectively. Only 200 labor hours and 400 machine hours are available for production. Time requirements to produce one unit of X and Y are as follows: What is the constraint on machine hours for Knoxville Manufacturing Company?
A) 10X + 90Y £ 200
B) 1X + 2Y £ 400
C) 5X + 1Y £ 400
D) 1X + 2Y £ 200