Figure 15-1 The following information relates to Lancashire Manufacturing:
To produce a unit of product: There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
Refer to Figure 15-1. What is the production rate?
A) 8.6 units per hour
B) 7 units per hour
C) 21 units per hour
D) 19 units per hour
Correct Answer:

Verified
Correct Answer:
Verified
Q4: An assessment of productive efficiency for all
Q7: The departments or cells that contain all
Q12: Which of the following conditions is NOT
Q26: Allocating efficiency chooses the least costly, technically
Q74: At the end of 2014, Diatomic Company
Q76: Information about Haulover Company is as follows:
Q77: Information about Kerkonian Corporation is as follows:
Q78: The Marakesh Company provides the following data:
Q81: Listed below are several possible combinations for
Q100: The value stream focuses on just value-added