Multiple Choice
Figure 15-1 The following information relates to Lancashire Manufacturing:
To produce a unit of product: There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
Refer to Figure 15-1. How long would it take to process the first unit of a 20-unit batch under a cellular manufacturing setup?
A) 21 minutes
B) 12 minutes
C) 19 minutes
D) 60 minutes
Correct Answer:

Verified
Correct Answer:
Verified
Q24: The accounting approach designed to support and
Q34: Productivity measurement is a quantitative assessment of
Q54: In a traditional manufacturing setup<br>A)there is significant
Q80: Which is NOT a benefit of lean
Q110: The value stream<br>A)is made up of all
Q143: The Marakesh Company provides the following data:
Q143: Explain the difference between partial and total
Q144: At the end of 2014, Diatomic Company
Q145: Information about DeLorean Corporation is as follows:
Q155: Partial measures allow managers to focus on