Multiple Choice
Setup time for a product is 14 hours. A firm that uses JIT and produces the same product has reduced setup time by 2 hours. Setup labor is $35 per hour. If the company wants to reduce non-value-added costs by 40 percent next year, the currently attainable standard for setup time would be
A) 6.8 hours.
B) 9.2 hours.
C) 8.6 hours.
D) 9.6 hours.
Correct Answer:

Verified