Under the UCC,a Delay in Delivery or Nondelivery,in Whole or in Part,is

Question 14

Multiple Choice

Under the UCC,a delay in delivery or nondelivery,in whole or in part,is not a breach in circumstances in which performance has been made ________ because a contingency has occurred that was not contemplated when the parties reached the agreement.


A) Unreasonable
B) Unprofitable
C) Impracticable
D) More difficult
E) Less profitable