Multiple Choice
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,the expected time to complete activity A is
A) 5.00 weeks.
B) 7.33 weeks.
C) 7.67 weeks.
D) 8.00 weeks.
Correct Answer:

Verified
Correct Answer:
Verified
Q8: Briefly describe the makeup of the project
Q12: A Gantt chart provides a visual display
Q36: Crashing activates with positive slack reduces a
Q64: A _ breaks down a project into
Q65: Issues of cultural diversity in project management
Q66: A project consists of the following four
Q69: A project consists of the following four
Q72: A project team is typically cross-functional consisting
Q73: A project consists of the following four
Q94: Earned value analysis reports a project's performance