The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 68

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the expected time to complete activity A is A) 5.00 weeks. B) 7.33 weeks. C) 7.67 weeks. D) 8.00 weeks.
Table 9.2
-Using Table 9.2,the expected time to complete activity A is


A) 5.00 weeks.
B) 7.33 weeks.
C) 7.67 weeks.
D) 8.00 weeks.

Correct Answer: