Multiple Choice
A product's usage is normally distributed with a weekly average demand of 2,000 units and a weekly standard deviation of 125. The lead time for the product is 4 weeks. If the company would like to have a service level of 90% for this product then the reorder point is approximately
A) 8,320 units.
B) 9,218 units.
C) 10,134 units.
D) 11,244 units.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Which of the following is not considered
Q18: Finished product is an example of a
Q32: The demand for an electronic component is
Q35: Shortage costs are easier to determine than
Q72: The demand for an electronic component is
Q77: The average inventory can be calculated by
Q81: The number of orders can be calculated
Q88: The ability to effectively satisfy internal or
Q91: Hedging involves buying larger amounts of inventory
Q92: What is the carrying cost using the