Multiple Choice
In capacity planning,the feasibility of the sales and operations production plan is verified by a
A) resource requirements plan.
B) rough-cut capacity plan.
C) capacity requirements plan.
D) master production schedule.
Correct Answer:

Verified
Correct Answer:
Verified