Multiple Choice
Given the following MRP matrix for Item C:
If each order cost $500 and the holding cost is $0.75 per item per period,then using the Periodic Order Quantity lot sizing technique,the Projected on Hand at the end of period 7 would be
A) 330
B) 270
C) 0
D) 140
Correct Answer:

Verified
Correct Answer:
Verified