Games R Us Company makes children's board games. One popular game requires three hours of processing time, seven hours of waiting time, and five hours of moving time. What is the manufacturing cycle efficiency (MCE) for Games R Us Company?
A) 16.7%
B) 20.0%
C) 25.0%
D) 33.0%